Elite Beach Resort
A case study in delivery.
2,474 residential units and a 150-room hotel with restaurants, retail, swimming pools and health club across 600,000 m².
Complete project management for the owner: scheduling, cost estimating, cash-flow forecasting, procurement, bid analysis and evaluation, time and cost control, and quality assurance.
The brief.
Large residential programmes live and die on repetition, cash-flow discipline and on-time hand-over of finished homes. HG applied a structured PM system to plan the works at building, cluster and community levels — sequencing infrastructure, superstructure, MEP and hand-over trades so units could be released to owners in coordinated tranches.
Execution.
Delivery was organised by cluster and floor, with rolling four-week look-aheads driving crew allocation and material call-off. Contract administration, claims analysis and quality inspections ran in parallel so hand-over packs were complete when units were physically ready.
Completion.
Homes were handed over in structured tranches with defect rates within owner tolerance, supported by a full record of scope changes, valuations and progress backup. Repeat business followed on adjacent phases.
Every discipline HG performed on this engagement.
The full engagement scope, grouped by discipline. Each item was executed by the relevant HG subsidiary or an integrated delivery team on behalf of the owner, contractor or consortium.
- Scheduling
- Cash-flow forecasting
- Cost estimating
- Cost control
- Procurement
- Bid analysis
- Quality assurance
- Evaluation
- Time